Greenfield Construction of $1.85B Chemical Complex

St. James, LA


Bronco’s work scope includes installing, maintaining, and erecting all structural, mechanical, and piping associated with the plant's cooling water and flare systems.

Quantities:

  • Installed 24,000 LF Pipe 68” thru 1”

  • 26,000 LI of Welding (CS, SS, Chrome)

  • 700 Tons of Structural Steel

  • Assembled and Set 3 - 4100HP, 165,655 LBS Cooling Water Pumps

Client:
YCI Methanol One

Contract Value:
$5 million

Manhours:
65,000

Safety record:
0 recordable incidents

Services:
Mechanical

Year:
2019