New Water Treatment Facility for Nucor in South Carolina Completed

We're proud to announce the successful completion of the new water treatment facility that will service the new galvanize line expansion at the Nucor Berkeley Facility in South Carolina.

From in-house piping design and 3D modeling through pre-commissioning and startup assistance, our team self-performed every discipline on site, delivering a fully integrated solution for our client.

Here's what we delivered on-time and under budget:

  • 44 Pieces of equipment installed

  • 120 Tons of structural steel fabricated and installed

  • 16,000lf of piping fabricated and installed

  • 2,715 Welds

  • 190’x80’ Metal building erected with standing seam roof

  • 36,000 Work hours recordable free

  • Peak head count 45

  • 100% weld acceptance

Thank you to our hard-working team that executed this project!